Procedure of completion of the construction of the biogas plant
(Click to see more detailed steps)
- I. Preparation of the investment
- determination of needs and possibilities of the Investor
- preliminary talks, decisions
- site inspections
- preliminary selection of technology
- analysis of location of the existing infrastructure
- determination of the building development area
- assessment of the possibilities of the use and integration of the existing systems
- assessment of availability of the substrate
- required studies and laboratorial tests
- characterisation of wastewater (temperature, pH, COD, BOD, nitrogen, phosphorus, chlorine, sulphates, potassium, suspended matter)
- assessment of costs, subsidies, profitability
- estimated assessment of the costs of investment
- indication of the sources of financing
- acceptance of design assumptions
- determination of conditions of cooperation
- time limits
- payments
- warranties
- aid in obtaining subsidies
- determination of needs and possibilities of the Investor
- II. Design stage
- technological design of the installation – concept
- determination of technology and range of the investment works
- settlement with the Investor
- building design for building permit
- site development plan
- conditions of connection to the electric power network
- conditions of rainwater disposal
- conditions of connection to the water supply network
- conditions of wastewater disposal
- decision on land development conditions
- design for construction works
- design for architectural works
- design for works related to wastewater systems
- design for works related to water supply systems
- design for ventilation works
- design for electrical works
- design for electric power works
- design for control and measuring instrumentation
- design for technological works
- submission of the design to relevant authorities
- obtaining a decision on environmental conditions of an agreement to complete the enterprise
- application + map to the City Hall
- verification of the application and establishment of Parties by the City Hall
- provision of the sanitary and epidemiological station
- provision of the City Hall on the necessity of preparing a report on environmental impact or not
- preparation of a report (optional)
- decision of the sanitary and epidemiological station
- issuance of decision on environmental conditions
- working design, specification of the equipment
- technological working design
- architectural working design
- structural working design
- working designs of site installations
- working design of the networks covered by the site development plan
- instruction manuals for operation of: the facility, systems and plants related to the facility
- working designs of infrastructure
- technological design of the installation – concept
- III. Completion (execution) stage
- purchase and supply of materials
- performance and completion of the equipment
- construction works
- assembly of site installations
- assembly of technological equipment
- site assembly of control and measuring systems
- installation trials, preparation for operation
- IV. Operational stage
- tank inoculation and commissioning
- trial operation
- acceptance
- observation of the process and control of parameters
- guarantee and post-guarantee service
- operational service of the facility
- economic and technical analysis of the facility, verification of design assumptions